home *** CD-ROM | disk | FTP | other *** search
- #2650
- @001 Enter the name of the OWNER:
- @002 Enter the name of the CONTRACTOR:
- @100 Enter name of individual to receive draw request:
- @101 Enter street address of OWNER:
- @102 Enter city, state, zip code of OWNER:
- @103 Enter name/number of job:
- @200 Enter the draw number:
- @104 Draw is requested for period beginning:
- @105 Draw is requested for period ending:
- !106 Enter in numerals the total draw request:
- @116 Enter the date of original contract:
- #2651/#2652/#2653 Draw was based on:
- per centage of completion
- stage of completion
- cost plus formula
- #if#2651
- @117 Enter the percentage of completion:
- !107 Enter the total draw received to date (in numerals):
- !108 Enter the total present retainage (in numerals):
- #endif
- #if#2652
- @109/@109/@109/@109 Enter the stage of completion:
- rough in
- first inspection
- final inspection
- KEY IN VALUE
- #endif
- #if#2653
- !110 Enter total expenditure to date (in numerals):
- #2654 Is a architect certificate or other support attached?
- #if#2654
- @112/@112/@112 The following is attached:
- architect's certificate
- inspection report
- KEY IN VALUE
- #endif
- #2655
- #end control section
- #2650
- /* Para. 2650: Draw request */
-
- To: @001
-
- Attention: @100
-
- @101
-
- @102
-
-
- Dated: ____________________
-
-
- Re: @103 Job
-
-
- Draw request number: @200
-
- Draw request from period @104 to @105
-
-
- Total amount of draw request: $ @106 (!106 dollars)
-
-
- Pursuant to the contract of @116, and any change orders thereto,
- @002 requests a total draw in the amount indicated.
- #2651
- /* Para. 2651: Draw based upon % completion */
-
-
- The present per centage completion of the project is @117 per
- cent. The total draws requested and paid to date equal $ @107
- (!107 dollars) and $ @108(!108 dollars) is the present retainage.
-
- #2652
- /* Para. 2652: Draw based on rough in/etc */
-
-
- The project has reached the @109 stage.
-
- #2653
- /* Para. 2653: Draw based on cost plus */
-
-
- The total expenditure to date is $ @110 (!110 dollars).
-
- #2654
- /* Para. 2654: Architect certificate or other infor */
-
- A @112 is attached.
-
-
- #2655
-
-
- Dated: ______________________
-
-
-
-
- _____________________________________________
-
- For @002, CONTRACTOR